Projects Recently Completed
- Student Apartment Complex
Project cost: $45 million
Construction start: Winter 2009/2010
Construction finish: Summer 2011
- Smart Classroom Renovations
Project cost: $809,000
Construction start: Spring 2011
Construction finish: Summer 2011
- Underground Utility Replacements, Scajaquada Complex
Project cost: $807,000
Construction start: Spring 2011
Construction finish: Fall 2011
- Roof Replacements
Project cost: $2.3 million
Construction start: Spring 2011
Construction finish: Winter 2011/2012
Spring 2012 Capital Projects
- Science and Mathematics Complex
Project cost: $103.4 million
Construction start: Summer 2009
Construction finish: Spring 2016
- Technology Building
Project cost: $38 million
Construction start: Summer 2011
Construction finish: Summer 2013
- Rockwell Hall Third Floor Renovation
Project cost: $9.5 million
Construction start: Summer 2011
Construction finish: Summer 2012
- Student Union Third Floor Rehabilitation
Project cost: $5.3 million
Construction start: Spring 2012
Construction finish: Spring 2013
- Underground Utility Replacements, Rockwell Quad & Vicinity
Project cost: $11.2 million
Construction start: Spring 2011
Construction finish: Winter 2013/2014
- Campus West Rehabilitation for Surge Space
Consultant: Wendel Companies
Project cost: $1.2 million
Construction start: Spring 2012
Construction finish: Summer 2012
- Tower 4 Rehabilitation
Project cost: $7 million
Construction start: Spring 2012
Construction finish: Summer 2013
Future Projects
- Houston Gymnasium Rehabilitation
Project cost: $28 million
Construction start: Fall 2012
Construction finish: Winter 2014
- Upton Hall Renovation
Project cost: $42.6 million (Phase 1)
Construction start: Fall 2013
Construction finish: Summer 2015
- Caudell Hall Renovation
Project cost: $21.2 million
Construction start: Fall 2013
Construction finish: Summer 2015
- Athletic Stadium
Project cost: $40.3 million
Construction start: To be determined
Construction finish: To be determined