CONSTRUCTION

Architect: Cannon Design
Construction manager: Lend Lease
Project cost: $52.3 million
Construction start: Summer 2009
Construction finish: Fall 2012
Occupancy: Spring 2013        

 

    

 b 

Photos: November 2012

Phase 1 construction of the Science and Mathematics Complex provides an expansive multi-story atrium, an advanced imaging suite, and state-of-the-art research and teaching facilities for Buffalo State's Biology, Chemistry, and  Earth Sciences and Science Education departments, as well as the Great Lakes Center