Capital Projects Recently Completed

Technology Building

   Project cost: $36.5 million
   Construction start:  Summer 2011
   Construction finish: Summer 2013


 

Scajaquada Tower 4 Renovation

   Project cost: $7.6 million
   Construction start: Spring 2012
   Construction finish: Summer 2013


 

Underground Utility Replacements, Rockwell Quadrangle & Vicinity

   Project cost: $10.2 million
   Construction start: Spring 2012
   Construction finish: Fall 2013
 




Argo Tea Café

   Project cost: $630,000
   Construction start: Summer 2013
   Construction finish: Spring 2014

 
 


Buckham Hall Rehabilitation for Surge Space: Supporting the Renovation of Caudell Hall

   Project cost: $1.6 million
   Construction start: Fall 2013
   Construction finish: Spring 2014



 

Capital Projects in Construction, Summer 2014

Science and Mathematics Complex, Phase 2

   Project cost: $30.9 million
   Construction start: Fall 2013
   Construction finish: Fall 2015


 


Caudell Hall Renovation

   Project cost: $21.2 million
   Construction start: Summer 2014
   Construction finish: Summer 2016




Houston Gymnasium Rehabilitation

   Project cost: $27 million
   Construction start: Fall 2012
   Construction finish: Summer 2014
   Occupancy:  Summer 2014



Press Box
    Project cost: $1.9 million
    Construction start: Late summer 2014
    Construction finish: Spring 2015 

                      
          
     
          Scajaquada Tower 1 Renovation

     Project cost: $11.8 million
     Construction start: Summer 2014
     Construction finish: Summer 2015

             




Exterior Signage Replacement

   Project cost: $1.1 million
   Construction start: Summer 2014
   Construction finish: Fall 2014 

 
 


Capital Projects in Design or Bidding Phase, Summer 2014


Upton Hall Renovation, Phase 1

   Project cost: $48.3 million
   Construction start: To be determined
   Construction finish: To be determined